| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Morgan State Banner Implementation | 715 days | Mon 6/9/03 | Fri 3/3/06 | | 0% |
| 2 | | | | | | |
| 3 | BANNER Technical Support | 10 days | Mon 8/4/03 | Fri 8/15/03 | | 0% |
| 4 | TN Oracle Install | 5 days | Mon 8/4/03 | Fri 8/8/03 | Bill Edwards | 0% |
| 5 | TN Banner Install | 5 days | Mon 8/4/03 | Fri 8/8/03 | Danette Miller | 0% |
| 6 | TN Oracle Follow-Up Visit | 5 days | Mon 8/11/03 | Fri 8/15/03 | Bill Edwards | 0% |
| 7 | Oracle Training Classes | 879 days? | Tue 2/22/00 | Fri 7/4/03 | | 0% |
| 8 | TN Intro to Oracle | 32 hrs | Tue 7/1/03 | Fri 7/4/03 | | 0% |
| 9 | TN Oracle DBA I | 32 hrs | Tue 7/1/03 | Fri 7/4/03 | | 0% |
| 10 | TN Oracle DBA II | 32 hrs | Tue 7/1/03 | Fri 7/4/03 | | 0% |
| 11 | TN Intro to BANNER Admin | 32 hrs | Tue 7/1/03 | Fri 7/4/03 | | 0% |
| 12 | TN Forms 4.5 | 32 hrs | Tue 7/1/03 | Fri 7/4/03 | | 0% |
| 13 | TN SQL/PL-SQL/SQL Loader | 32 hrs | Tue 7/1/03 | Fri 7/4/03 | | 0% |
| 14 | TN PRO C & Conv. Standards | 32 hrs | Tue 7/1/03 | Fri 7/4/03 | | 0% |
| 15 | TN Banner General & Security | 32 hrs | Tue 7/1/03 | Fri 7/4/03 | | 0% |
| 16 | Remote DBA Consulting | 1 day? | Tue 2/22/00 | Tue 2/22/00 | | 0% |
| 17 | Visit 1 | 1 day? | Tue 2/22/00 | Tue 2/22/00 | | 0% |
| 18 | Visit 2 | 1 day? | Tue 2/22/00 | Tue 2/22/00 | | 0% |
| 19 | Visit 3 | 1 day? | Tue 2/22/00 | Tue 2/22/00 | | 0% |
| 20 | Visit 4 | 1 day? | Tue 2/22/00 | Tue 2/22/00 | | 0% |
| 21 | Visit 5 | 1 day? | Tue 2/22/00 | Tue 2/22/00 | | 0% |
| 22 | Visit 6 | 1 day? | Tue 2/22/00 | Tue 2/22/00 | | 0% |
| 23 | Visit7 | 1 day? | Tue 2/22/00 | Tue 2/22/00 | | 0% |
| 24 | Visit 8 | 1 day? | Tue 2/22/00 | Tue 2/22/00 | | 0% |
| 25 | Remote DBA Management | 200 days | Mon 7/7/03 | Fri 4/9/04 | Tim Tinkham[1%] | 0% |
| 26 | | | | | | |
| 27 | BANNER Finance Implementation | 275 days | Mon 8/18/03 | Fri 9/3/04 | | 0% |
| 28 | FI BPA (BPA Specialist) | 5 days | Mon 8/18/03 | Fri 8/22/03 | Smith_Matthew_W.F. | 0% |
| 29 | FI BPA (Finance Consultant) | 5 days | Mon 8/18/03 | Fri 8/22/03 | Kreutz_Margarette_T. | 0% |
| 30 | FI BPA (Doc Prep - BPA Specialist) | 5 days | Mon 8/25/03 | Fri 8/29/03 | Smith_Matthew_W.F. | 0% |
| 31 | FI BPA (Doc Prep - Finance Consultant) | 5 days | Mon 8/25/03 | Fri 8/29/03 | Kreutz_Margarette_T. | 0% |
| 32 | FI Review Models | 5 days | Mon 9/1/03 | Fri 9/5/03 | Kreutz_Margarette_T.[60%] | 0% |
| 33 | FI Initial Tech Training | 5 days | Mon 9/29/03 | Fri 10/3/03 | Neil_David | 0% |
| 34 | FI System Overview & COA | 5 days | Mon 10/6/03 | Fri 10/10/03 | Kreutz_Margarette_T.[90%] | 0% |
| 35 | FI COA, On-Line Inquiry and Rpts | 5 days | Mon 11/17/03 | Fri 11/21/03 | Kreutz_Margarette_T. | 0% |
| 36 | FI Purchasing, AP and Bank Recon. | 5 days | Mon 12/1/03 | Fri 12/5/03 | Kreutz_Margarette_T. | 0% |
| 37 | FI Rules, Security, Approvals | 5 days | Mon 12/15/03 | Fri 12/19/03 | Kreutz_Margarette_T.[90%] | 0% |
| 38 | FI Research Accounting & Proposals | 5 days | Mon 1/26/04 | Fri 1/30/04 | Kreutz_Margarette_T. | 0% |
| 39 | FI Fixed Assets | 5 days | Mon 2/16/04 | Fri 2/20/04 | Kreutz_Margarette_T. | 0% |
| 40 | FI Budget Development & Posn. Ctl. | 5 days | Mon 3/1/04 | Fri 3/5/04 | Kreutz_Margarette_T.[90%] | 0% |
| 41 | FI Account Receivable | 5 days | Mon 3/15/04 | Fri 3/19/04 | Kreutz_Margarette_T. | 0% |
| 42 | FI Interfaces Trip | 5 days | Mon 3/29/04 | Fri 4/2/04 | Kreutz_Margarette_T. | 0% |
| 43 | FI Cost Accounting & Stores Inventory | 5 days | Mon 4/12/04 | Fri 4/16/04 | Kreutz_Margarette_T. | 0% |
| 44 | FI Gen'l Consulting I - Workflow | 5 days | Mon 5/3/04 | Fri 5/7/04 | Kreutz_Margarette_T.[70%] | 0% |
| 45 | FI Gen'l Consulting II - Workflow | 5 days | Mon 5/24/04 | Fri 5/28/04 | Kreutz_Margarette_T.[70%] | 0% |
| 46 | FI Gen'l Consulting III - Workflow | 5 days | Mon 5/31/04 | Fri 6/4/04 | Kreutz_Margarette_T.[70%] | 0% |
| 47 | FI Validate Procedures | 5 days | Mon 6/14/04 | Fri 6/18/04 | Kreutz_Margarette_T.[90%] | 0% |
| 48 | FI Conversion Planning | 5 days | Mon 6/28/04 | Fri 7/2/04 | Kreutz_Margarette_T.[70%] | 0% |
| 49 | FI GO LIVE Support - Preparation | 23.81 days | Mon 5/31/04 | Thu 7/1/04 | Kreutz_Margarette_T.[21%] | 0% |
| 50 | FI GO LIVE Support - Week of | 5 days | Thu 7/1/04 | Wed 7/7/04 | Kreutz_Margarette_T. | 0% |
| 51 | FI Year-End Preparation | 5 days | Mon 8/30/04 | Fri 9/3/04 | Kreutz_Margarette_T. | 0% |
| 52 | | | | | | |
| 53 | BANNER HR Implementation | 350 days | Mon 9/15/03 | Fri 1/14/05 | | 0% |
| 54 | HR BPA (BPA Specialist) | 0 days | Mon 9/15/03 | Mon 9/15/03 | Smith_Matthew_W.F. | 0% |
| 55 | HR BPA (HR Consultant) | 0 days | Mon 9/15/03 | Mon 9/15/03 | Briggs_Jonathan_R | 0% |
| 56 | HR BPA (Doc Prep - BPA Specialist) | 0 days | Mon 9/29/03 | Mon 9/29/03 | Smith_Matthew_W.F.[50%] | 0% |
| 57 | HR BPA (Doc Prep - HR Consultant) | 0 days | Mon 9/29/03 | Mon 9/29/03 | Briggs_Jonathan_R[50%] | 0% |
| 58 | HR Review Models | 5 days | Mon 1/5/04 | Fri 1/9/04 | Briggs_Jonathan_R[60%] | 0% |
| 59 | HR Initial Tech Training | 5 days | Mon 1/19/04 | Fri 1/23/04 | Farley_Laurene | 0% |
| 60 | HR Navigation, General Person | 5 days | Mon 2/16/04 | Fri 2/20/04 | Briggs_Jonathan_R[90%] | 0% |
| 61 | HR Letter Generation | 5 days | Mon 3/15/04 | Fri 3/19/04 | Briggs_Jonathan_R | 0% |
| 62 | HR Employee , Position Control, Budgeting | 5 days | Mon 4/19/04 | Fri 4/23/04 | Briggs_Jonathan_R | 0% |
| 63 | HR Benefits, Deductions, COBRA | 5 days | Mon 5/17/04 | Fri 5/21/04 | Briggs_Jonathan_R[90%] | 0% |
| 64 | HR General Consulting | 5 days | Mon 6/21/04 | Fri 6/25/04 | Briggs_Jonathan_R[90%] | 0% |
| 65 | HR Time Entry, Payroll | 5 days | Mon 7/12/04 | Fri 7/16/04 | Briggs_Jonathan_R[90%] | 0% |
| 66 | HR Validate Procedures | 5 days | Mon 8/23/04 | Fri 8/27/04 | Briggs_Jonathan_R[90%] | 0% |
| 67 | HR Conversion Planning | 5 days | Mon 9/20/04 | Fri 9/24/04 | Briggs_Jonathan_R[70%] | 0% |
| 68 | HR GO LIVE Support - Preparation | 5 days | Mon 10/18/04 | Fri 10/22/04 | Briggs_Jonathan_R | 0% |
| 69 | HR GO LIVE Support - Week of | 5 days | Mon 1/3/05 | Fri 1/7/05 | Briggs_Jonathan_R | 0% |
| 70 | HR Year-End Preparation | 5 days | Mon 1/10/05 | Fri 1/14/05 | Briggs_Jonathan_R | 0% |
| 71 | | | | | | |
| 72 | BANNER Student Implementation | 605 days | Mon 11/10/03 | Fri 3/3/06 | | 0% |
| 73 | Student BPA (BPA Specialist) | 0 days | Mon 9/13/04 | Mon 9/13/04 | Smith_Matthew_W.F. | 0% |
| 74 | Student BPA (Student Consultant) | 0 days | Mon 9/13/04 | Mon 9/13/04 | Foshee_Kenneth_H. | 0% |
| 75 | Student BPA (Doc Prep - BPA Specialist) | 0 days | Mon 9/27/04 | Mon 9/27/04 | Smith_Matthew_W.F.[20%] | 0% |
| 76 | Student BPA (Doc Prep - Student Consultant) | 0 days | Mon 9/27/04 | Mon 9/27/04 | Foshee_Kenneth_H.[20%] | 0% |
| 77 | ST Review Models | 5 days | Mon 10/4/04 | Fri 10/8/04 | Foshee_Kenneth_H.[60%] | 0% |
| 78 | ST Initial Tech Training | 5 days | Mon 11/8/04 | Fri 11/12/04 | McCann_Shawn_L | 0% |
| 79 | ST Overview, Navigation/General Person | 5 days | Mon 12/13/04 | Fri 12/17/04 | Foshee_Kenneth_H.[90%] | 0% |
| 80 | ST Catalog/Schedule, Loc Mgmt & Faculty Crossover | 5 days | Mon 1/3/05 | Fri 1/7/05 | Foshee_Kenneth_H. | 0% |
| 81 | ST Recruitment, Admissions, Communications Plans | 5 days | Mon 2/7/05 | Fri 2/11/05 | Foshee_Kenneth_H. | 0% |
| 82 | ST General Student/Registration/Fee Assessment | 5 days | Mon 3/7/05 | Fri 3/11/05 | Foshee_Kenneth_H. | 0% |
| 83 | ST Accounts Receiveable Session 1 | 5 days | Mon 4/4/05 | Fri 4/8/05 | Foshee_Kenneth_H. | 0% |
| 84 | ST Accounts Receiveable Session 2 | 5 days | Mon 5/2/05 | Fri 5/6/05 | Foshee_Kenneth_H.[70%] | 0% |
| 85 | ST Academic History | 5 days | Mon 6/6/05 | Fri 6/10/05 | Foshee_Kenneth_H. | 0% |
| 86 | ST Object Access, Faculty Load, Loc. Mgmt, Housing | 5 days | Mon 7/11/05 | Fri 7/15/05 | Foshee_Kenneth_H. | 0% |
| 87 | ST Letter Generation, Population Selection, Job Submission, Object Access | 5 days | Mon 8/8/05 | Fri 8/12/05 | Foshee_Kenneth_H. | 0% |
| 88 | ST CAPP Session 1 | 5 days | Mon 9/12/05 | Fri 9/16/05 | Foshee_Kenneth_H.[90%] | 0% |
| 89 | ST CAPP Session 2 | 5 days | Mon 10/10/05 | Fri 10/14/05 | Foshee_Kenneth_H.[70%] | 0% |
| 90 | ST Validate Procedures | 5 days | Mon 11/7/05 | Fri 11/11/05 | Foshee_Kenneth_H.[90%] | 0% |
| 91 | ST Conversion Planning | 5 days | Mon 12/12/05 | Fri 12/16/05 | Foshee_Kenneth_H.[70%] | 0% |
| 92 | ST GO LIVE Support - Preparation | 5 days | Mon 1/16/06 | Fri 1/20/06 | Foshee_Kenneth_H. | 0% |
| 93 | ST GO LIVE Support - Week of | 5 days | Mon 2/27/06 | Fri 3/3/06 | Foshee_Kenneth_H. | 0% |
| 94 | | | | | | |
| 95 | BANNER Financial Aid Implementation | 520 days | Mon 2/9/04 | Fri 2/3/06 | | 0% |
| 96 | FAID BPA (BPA Specialist) | 0 days | Mon 1/10/05 | Mon 1/10/05 | Smith_Matthew_W.F. | 0% |
| 97 | FAID BPA (FAID Consultant) | 0 days | Mon 1/10/05 | Mon 1/10/05 | Leiter_Soule | 0% |
| 98 | FAID BPA (Doc Prep - BPA Specialist) | 0 days | Mon 1/17/05 | Mon 1/17/05 | Smith_Matthew_W.F.[50%] | 0% |
| 99 | FAID BPA (Doc Prep - FAID Consultant) | 0 days | Mon 1/17/05 | Mon 1/17/05 | Leiter_Soule[50%] | 0% |
| 100 | FA Review Models | 5 days | Mon 2/7/05 | Fri 2/11/05 | Leiter_Soule[60%] | 0% |
| 101 | FA Initial Tech Training | 5 days | Mon 3/7/05 | Fri 3/11/05 | Kerr_James_A | 0% |
| 102 | FA Navigation, Overview, Record Creation and EDE Processing | 5 days | Mon 4/4/05 | Fri 4/8/05 | Leiter_Soule | 0% |
| 103 | FA Applicant Tracking, Budgeting and Need Analysis | 5 days | Mon 5/2/05 | Fri 5/6/05 | Leiter_Soule | 0% |
| 104 | FA Funds Management, Student Employment | 5 days | Mon 6/6/05 | Fri 6/10/05 | Leiter_Soule | 0% |
| 105 | FA Packaging (Loans) and Letter Generation | 5 days | Mon 7/11/05 | Fri 7/15/05 | Leiter_Soule | 0% |
| 106 | FA Disbursements and Population Selection | 5 days | Mon 8/8/05 | Fri 8/12/05 | Leiter_Soule | 0% |
| 107 | FA Award History, Transcripts, Common Functions, | 5 days | Mon 9/12/05 | Fri 9/16/05 | Leiter_Soule | 0% |
| 108 | FA Validate Procedures | 5 days | Mon 10/10/05 | Fri 10/14/05 | Leiter_Soule[90%] | 0% |
| 109 | FA Conversion Planning | 5 days | Mon 11/14/05 | Fri 11/18/05 | Leiter_Soule[70%] | 0% |
| 110 | FA GO LIVE Support - Preparation | 5 days | Mon 1/9/06 | Fri 1/13/06 | Leiter_Soule | 0% |
| 111 | FA GO LIVE Support - Week of | 5 days | Mon 1/30/06 | Fri 2/3/06 | Leiter_Soule | 0% |